Procedure for issuing the permit for the authorization of the execution of constructions of any kind located in the vicinity of the objectives/natural gas distribution systems operated by Distrigaz Sud Retele SRL*
favorite_border
Add favorite
Procedure
Online
Companii
Cetateni
National
Details
Based on Law 50/1991 regarding the authorization of construction works, with subsequent modifications and completions, and Order 47/2003 for the approval of the Procedure for issuing the approval for authorizing the execution of constructions located in the vicinity of objectives/systems in the oil and natural gas sector, Distrigaz Sud Retele (DGSR) issues upon request:
- Siting approvals - issued for construction/demolition works; the fee is calculated based on the studied area. Examples of requests:
- extension, consolidation, reorganization, re-compartmentalization, existing construction
- construction of new building with/without connections, pedestrian and road alleys, land fencing
- balcony construction, creation of outside access opening, change of space destination
- demolition of existing constructions
- legalization of construction
- arrangement of park, parking lot, etc.
- Route approvals - issued for works for utilities networks/connections/services/roads; the fee is calculated based on the length of the studied route. Examples of requests:
- extensions/establishment of water, sewer, electric, heating, telephone, gas pipelines
- rehabilitation/establishment of roads, asphalting
- diversion of water, sewer, electric, heating, telephone, gas pipelines
- replacement/rehabilitation/modernization of water, sewer, electric, heating, telephone, gas pipelines
- water sewer connection/branch
- thermal connections
- electrical connection
- gas connections/connections
- replacement of tram line; extension of trolleybus line etc.
- modernizations, road rehabilitations, etc.
- Principle approvals - are issued if the client requests information regarding the existence or not of DGSR networks on a land plot, in the case of notarial operations, feasibility or pre-feasibility studies or when preparing PUD, PUZ, PUG documentations; the fee is calculated based on the studied area. PUG and general interest PUZ/PUD are not charged; fee exemption for PUZ/PUD applies based on a letter from the public institution accompanying the documentation, stating that the objective falls under the provisions of Law no. 350/2001 art. 56 para. 3. Examples of requests:
- PUD, PUZ, PUG
- notarial operations: alienation of land, subdivision, concession, etc.
- network marking
- FS or pre FS
- construction site organization
The approval represents the written response to the applicant's request, with mandatory technical character, in which the standpoint regarding the fulfillment of coexistence conditions of the proposed objective with respect to the natural gas distribution networks of the operator Distrigaz Sud Retele is specified.
The approval is obtained only after submitting the complete documentation consisting of: standard request, necessary documents mentioned in the request and proof of payment. All details regarding the procedure for issuing approvals can be found by accessing https://www.distrigazsud-retele.ro/obtinerea-de-avize/.
Siting and route approvals are issued within a maximum of 5 working days from the date of submission of the complete documentation.
Principle approvals are issued within a maximum of 15 working days from the date of submission of the complete documentation.
The documentation may be submitted by a consultant, designer, or any other natural or legal person authorized by the holder of the urbanism certificate/applicant.
Requests can be submitted ONLINE using the form in the contact section of the Distrigaz Sud Rețele website Avize (distrigazsud-retele.ro) or DIRECTLY at the Distrigaz Sud Retele offices.
The standard request can be found here:
Eliberare avize | Distrigaz Sud Rețele (distrigazsud-retele.ro)
Eliberare avize | Distrigaz Sud Rețele (distrigazsud-retele.ro)
For documentation with plans larger than A3 format, physical submission of these at the headquarters of Distrigaz Sud Retele is mandatory and uploaded on CD in .dwg electronic format, scale 1:500 or 1:1000, in Stereo '70 coordinate system with title block, legend and cleared of unused graphic elements and definitions – using the purge function.
The issuance of the approval consists of the following steps:
- checking the documentation and requesting completions, if necessary;
- issuing and sending the Payment Note corresponding to the type of requested approval; payment of the fee, presentation of proof of payment and the related documentation;
- registration of the request;
- documentation analysis and invoice issuance;
- identification and verification in the field/GIS MAP of the DGSR objectives and the location for which approval is requested;
- marking the DGSR objectives on the site plan, stamping the site plan and issuing the approval;
- delivering/sending the approval to the applicant.
The applied fees are valid starting with 01.08.2024, are included in the List of Services/Related Activities of Distrigaz Sud Retele and are under the provisions of Order 140/2015 of ANRE for setting regulated tariffs for activities related to the operation of the natural gas distribution system. Fees are calculated based on the land area (for siting approvals), the analyzed length (for route approvals) and/or based on the number of plans. Details regarding the value of the fees as well as their classification can be found by accessing Servicii și tarife | Distrigaz Sud Rețele (distrigazsud-retele.ro)
Fees are paid only based on the Payment Note (document reference in the payment document is mandatory).
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
FD 016 17 Request for granting the approval.*
Descarcă
The provided application form will be completed.*
Urbanism Certificate*
Descarcă
The Urbanism Certificate (copy), within the validity period, and/or the opportunity notice (copy) - for PUD/PUZ/PUG. Note: for information notices or utility connection notices, this document is optional.*
Technical memorandum regarding the construction work considered*
Descarcă
It will include: the name of the objective (work) and the purpose of the investment; description of the geometric elements and technical characteristics of the investment objectives; the structural system and the construction materials used; general data regarding the works that are the subject of the project; specialty reports, as applicable, technical connection approvals or solution sheets, etc.*
Area integration plan, at a scale of 1:25,000 ; 1:10,000; 1:5,000*
Descarcă
The plan on a topographic support, endorsed by the office of cadastre and real estate publicity, at a suitable scale depending on the dimensions of the site, with the location marked on the plan.*
Situation plan based on TOPO survey including the table with the Stereo 70 coordinate inventory, at a scale of 1:500 or 1:1000, which should include the location of constructions/connections within the proposed perimeter, as well as the related access roads, with title block and legend*
Descarcă
For documentation with plans in a format larger than A3, it is mandatory to physically submit them at the Distrigaz Sud Retele headquarters, in 2 copies and uploaded on a CD in electronic .dwg format, scale 1:500 or 1:1000, in the Stereo '70 coordinate system with title block, legend, and cleaned of unused graphic elements and definitions – purge function.*
Land register excerpt and/or the situation plan endorsed by OCPI*
Descarcă
Proof of title over land and/or constructions*
Descarcă
Documents attesting the beneficiary's ownership or possession rights (copy).*
Power of attorney for representation (as applicable)*
Descarcă
The power of attorney will be attached in scanned copy.*
CI/ Fiscal registration certificate or Certificate of registration for VAT purposes*
Descarcă
In the case where the request is submitted by a representative, the ID/ Fiscal Registration Certificate or VAT Registration Certificate will also be submitted for them.*
Proof of payment*
Descarcă
Payment confirmation accompanied by the bill*
Other documents*
Descarcă
Any other documents that you consider important in the process of obtaining approval will be uploaded.*
Fees
Title
Payment method
Value
Currency
Taxă variabilă
OP
Deadlines
Resolution time:
7
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
5
Calendar days
Legislation
Appeal routes
In the case of a dispute between the beneficiary and Distrigaz Sud Retele, the provisions of common law apply.
*Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
14 March 2025
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Distrigaz Sud Retele*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Bucuresti, Sectorul 4, Blv. Marasesti 4-6
Telefon:
0213012016
Fax:
0213012016
Email:
contact@distrigazsud-retele.ro
Table of contents
Competent entities
DISTRIGAZ SUD RETELE
DISTRIGAZ SUD RETELE
DISTRIGAZ SUD RETELE Bucuresti
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve