Technical notice ANIF for obtaining the Building Permit for investment objectives located within the built-up area of localities - for individuals*

favorite_border
Add favorite
Procedure
Online
Companii
National
Cross-border

Details
The Central Unit or the Territorial Branch of Land Improvements coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.

*
Entitled persons
Regulated professions
Required documents

Denumire

Descriere

Obligatoriu

Semnătură digitală

Tip document

Descarcă


-
The request of the beneficiary or the owner, as applicable, specifically mentioning the area, the investment to be carried out, signature*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Copy of the identity document*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Notarial power of attorney/mandate/resolution of the general assembly of associations, decision of the sole associate/representative of the associative form, in copy, copy of the ID card of the authorized person, or copy of the passport for the authorized private individual with domicile abroad*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
In case of representation Following the notification of the issuance of the permit, the original documents will be presented when collecting it from the office*
Copy of the ownership document or another valid land possession document concluded, with notarized authentication*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Examples: The ownership title, sale-purchase contract, donation contract, or concession, lease, rent, superficies contract will be presented*
The owner's consent for the implementation of the investment objective on the studied site or the administrator's consent for the implementation of the investment objective on the studied site*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
The first agreement will be sent as a copy, if the land is owned by another person than the owner. The second agreement will be sent as a copy, if the land belongs to the public/private domain of the state and also, following the notification of the issuance of the permit, upon collection of the permit from the headquarters, the document will be presented in original.*
Copy of the urbanism certificate (valid), accompanied by the zoning plan and the site plan*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Technical memorandum of the work describing the investment objective*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Government Decision/County Council/Local Council, regarding the declaration of public utility for investment objectives of national, county, and local interest, under the conditions of the law, as applicable*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Copies of payment documents*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Proof of payment*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Payment can be made by the following methods: - cash at the ANIF Mures Branch Headquarters - bank transfer at the bank unit - treasury ANIF ACCOUNT RO94TREZ4765017014911*
Land registry excerpt*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
The land register excerpt for information accompanied by the cadastral plan excerpt, issued by the office of cadastre and real estate publicity no more than 30 days prior to the date of submission of the documentation (except in cases where a construction permit is requested for the implementation and rehabilitation of land improvement infrastructure in accordance with the provisions of art. 33, para. (2), letter a) of Law 138/2004 with subsequent amendments and additions).*
Issued documents

Denumire

Tip document

Descarcă


-
ANIF technical notice for obtaining the Building Authorization for investment objectives located within the built-up area of localities - for individuals*
obligatoriu cu semnatură digitală disponibil și prin OOTS
Fees

Title

Payment method

Value

Currency


Taxă variabilă
OP
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
30
Calendar days
Notification deadline:
4
Calendar days
Legislation
Appeal routes
National legislation does not contain special provisions; in case of a dispute, common law provisions are applicable.


*
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated: 
04 September 2023
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Institution responsible with document: 
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Anif – Mures Territorial Branch of Land Improvements*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Zăgazului (in curte la S.C. MURESUL S.A.) nr. 14, Targu Mures, RO
Telefon: 0265262388
Fax: 0372007455
Email: mures@anif.ro
Table of contents

Competent entities

SERVICIUL PLAN INVESTIŢII EXPLOATARE PATRIMONIU ACHIZIŢII CONTRACTE
A.D.R.
This site is managed by the Romanian Digitalisation Authority and is an official website of the Romanian Government
Public Institutions
Need assistance?
EU Institutions
Info
Your Europe
PNRR
PNRR. Finanțat de Uniunea Europeană
UrmătoareaGenerațieUE
© 2024 roepas.ro