Technical notice ANIF FTIF Teleorman for obtaining the Building Permit for investment objectives located within the built-up area of localities - for legal entities*
favorite_border
Add favorite
Procedure
Online
Companii
National
Cross-border
Details
Teleoman Territorial Branch for Land Improvements coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
The request of the beneficiary or the owner, as applicable, specifically mentioning the area, the investment to be made, the signature*
Descarcă
Copy of the identity document*
Descarcă
Notarial power of attorney/delegation/resolution of the general assembly of associations, decision of the sole associate/representative of the associative form, in copy, copy of the ID card for the authorized person, natural person or the passport for the authorized natural person with domicile abroad*
Descarcă
Copy of the ownership deed or another valid land holding document, with a notarized authentication conclusion*
Descarcă
Examples: The title deed, sale-purchase contract, donation contract or concession, lease, rental, or superficies contract will be presented. With the exception of requests for the works provided for in art.7, para.1, subparagraph 4 of Law 50/1991 regarding the authorization of construction works, republished.*
The owner's consent for carrying out the investment project on the studied site or the administrator's consent for carrying out the investment project on the studied site*
Descarcă
The first agreement will be sent as a copy, in case the land is owned by a person other than the owner. The second agreement will be sent as a copy, in case the land belongs to the public/private domain of the state and also, following the notification for issuing the approval, upon collecting it from the office, the document will be presented in original.*
Copy of the urbanism certificate (valid), accompanied by the area location plan and the site plan*
Descarcă
Copies of payment documents*
Descarcă
Proof of payment*
Descarcă
Payment can be made through the following methods: - cash at the Territorial Branch of Land Improvements Teleorman - payment order at the banking unit - treasury ANIF ACCOUNT: RO13TREZ606510701X007248 Alexandria Treasury CUI: RO29275212 CIF: 29494840*
Land registry extract*
Descarcă
The land registry excerpt for information accompanied by the cadastral plan excerpt, issued by the office of cadastre and real estate publicity no more than 30 days before the date of submission of the documentation, (except in the case where the issuance of the construction permit is requested for the realization and rehabilitation of land improvement infrastructure in accordance with the provisions of art. 33, para. (2), letter a) of Law 138/2004 with subsequent amendments and completions). Except for requests for the works provided in art.7, para.1, index 4 of Law 50/1991 regarding the authorization of construction works, republished. And except for public utility investment works.*
Technical memo of the work in which the investment objective is described*
Descarcă
Copy after the ANIF Approval for drawing up the Zonal Urban Plan (PUZ) for checking the conditions imposed when issuing the approval (if applicable)*
Descarcă
The ANIF notice for the Zoning Urban Plan (PUZ) will be accompanied by the Local Council Decision approving the PUZ.*
Certificate of registration and certificate of findings from the Trade Registry or the document based on which the activity is carried out, in copy.*
Descarcă
Fees
Title
Payment method
Value
Currency
None
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
5
Calendar days
Legislation
- Law number
83
dated year
2018
ORDER no. 83 of February 23, 2018 for the approval of the Procedure regarding the permanent or temporary removal from agricultural use of lands located outside the built-up area of localities, as well as for the approval of the Procedure regarding the refund of the fee paid to the Land Improvement Fund.*
- Law number
83
dated year
2010
Emergency Ordinance no. 83 of 2010 regarding the exemption from payment of the fees provided in art. 42 para. (3), letter h of the Land Improvement Law no. 138 of 2004, for the removal from the agricultural circuit of lands necessary for the realization of objectives of national, county and local interest*
Appeal routes
The legislation does not contain special provisions regarding means of appeal, in the event of a dispute the common law provisions are applicable
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
21 November 2023
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Anif Teleorman Territorial Branch for Land Improvements*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
DN51A
Telefon:
0247361080
Fax:
0247361092
Email:
teleorman@anif.ro
Table of contents
Competent entities