This procedure regulates the method of issuing the reception report upon completion of the works within the Mogosoaia Commune City Hall.
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
Building permit and urban planning certificate*
Descarcă
According to Annex 1 of Law no.50/1991 – copy*
Completion reports by specialties*
Descarcă
Architecture, structure, installations, as applicable, and classification of the construction in the importance category*
Color photographs for the works subject to reception*
Descarcă
Energy certificate*
Descarcă
Copy*
The evidentiary document of the value of the work, with and without VAT*
Descarcă
Accounting note/Balance sheet for legal entities*
The site supervisor's point of view*
Descarcă
Cadastral measurements of the property subject to reception*
Descarcă
Site provisions*
Descarcă
If applicable*
Plans from the Building Permit*
Descarcă
Situation, levels, sections, colored facades*
The investor’s announcement to I.S.C., for the appointment of a representative in the commission (for constructions classified in categories "A", "B", "C" and works carried out with public funds)*
Descarcă
The investor's announcement to I.S.U. for the appointment of a representative in the commission (for types of works where their representative is mandatory)*
Descarcă
The investor's notification to the County Directorate of Culture, for the appointment of a representative in the commission (for works carried out on historical monuments)*
Descarcă
Land registry extract for information / certificate stating that no land registry has been opened for the property*
Descarcă
NOTICE regarding completion of works*
Descarcă
NOTICE regarding the completion of the notified works and the request for the participation of the UAT representative at the reception – form F_NOT_07 – average completion time 3-4 min.*
Declaration-consent*
Descarcă
According to the provisions of Regulation (EU) No. 679/2016 regarding the protection of natural persons with regard to the processing of personal data and the free movement of such data*
Communication regarding the completion of the works*
Descarcă
Form F_A_10 – average completion time 3-4 min*
Announcement of commencement of works*
Descarcă
Form F_A_08 – average completion time 3-4 min*
Fees
Title
Payment method
Value
Currency
None
Deadlines
Resolution time:
30
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
3
Calendar days
Legislation
Appeal routes
In the case of a dispute between the beneficiary and the competent authority, the common law provisions apply.
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
11 November 2026
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Mogosoaia Commune*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Sos. Bucuresti-Targoviste nr. 51, Mogosoaia, RO
Telefon:
0213516692
Fax:
0213516695
Email:
primaria@mogosoaia.ro
Table of contents
Competent entities
No Results Found
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve