Technical approval ANIF for obtaining the Construction Authorization for temporary construction works located outside the built-up area of localities (e.g. household annexes of agricultural holdings located outside the built-up area) - for individuals*

favorite_border
Add favorite
Procedure
Online
Cetateni
National
Cross-border

Details

The Central Unit or the Territorial Branch for Land Improvements coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.

*
Entitled persons
Regulated professions
Required documents

Denumire

Descriere

Obligatoriu

Semnătură digitală

Tip document

Descarcă


-
The request of the beneficiary or the owner, as the case may be, specifically mentioning the area, the investment to be made, signature/stamp (legal entities)*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Copy of the identity document*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Notarial power of attorney/delegation/decision of the general meeting of associations, decision of the sole associate/representative of the associative form, in copy, copy of the ID card of the authorized person, natural person or passport of the authorized person, natural person with domicile abroad*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
In case of representation Following the notification of the issuance of the permit, the original documents will be presented when picking it up from the office*
Proof of payment*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Payment can be made through the following methods: - cash at the central unit - bank transfer at the bank unit - treasury ANIF ACCOUNT: RO87TREZ021501701X022759*
Land registry excerpt*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Land registry excerpt for information, accompanied by the cadastral plan excerpt, issued by the office of cadastre and real estate publicity no more than 30 days before the date of submitting the documentation (except in the case where the building permit is requested for the creation and rehabilitation of land improvement infrastructure, in accordance with the provisions of art.33, para.(2), letter a) of Law 138/2004, as amended and supplemented).*
The technical memorandum of the work in which the investment objective is described*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Copy of the technical opinion from ANIF for obtaining the Building Permit or the ANIF Technical Agreement (as applicable), for verifying compliance with the conditions imposed when the opinion was issued*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Copy of the ownership deed or another valid land possession document concluded, with notarized authentication*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Examples: The ownership title, sale-purchase contract, donation contract, or the concession, lease, rental, superficie contract will be presented*
The owner's agreement for permanent or temporary removal from the agricultural circuit or the administrator's agreement for permanent or temporary removal from the agricultural circuit of the land*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
The first agreement will be sent as a copy, in the case where the land is owned by a person other than the owner. The second agreement will be sent as a copy, in the case where the land belongs to the public/private/state domain and also, following the notification for the issuance of the permit, when picking it up from the office, the document will be presented in original.*
Copies of payment documents*
Descarcă
Scanned document
obligatoriu cu semnatură digitală disponibil și prin OOTS
Issued documents

Denumire

Tip document

Descarcă


-
ANIF technical notice for obtaining the Building Permit for provisional construction works located outside the built-up areas of localities (e.g. outbuildings of agricultural holdings located outside the built-up area) - for individuals*
obligatoriu cu semnatură digitală disponibil și prin OOTS
Fees

Title

Payment method

Value

Currency


None
Deadlines
Resolution time:
5
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
4
Calendar days
Legislation
Appeal routes

National legislation does not contain special provisions; in the event of a dispute, the general legal provisions are applicable.

*
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated: 
27 July 2022
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Institution responsible with document: 
Publicat de către: 
A paragraph is a self-contained unit of a discourse in writing dealing with a particular point or idea. Paragraphs are usually an expected part of formal writing, used to organize longer prose.
Anif Territorial Branch for Land Improvements Arad*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
strada. Splaiul Mures, nr. 6/D Arad
Telefon: 0257/280955
Fax: 0257/281915
Email: arad@anif.ro
Table of contents

Competent entities

SERVICIUL TEHNIC INVESTITII, ACHIZITII, CONTRACTE, AVIZE
A.D.R.
This site is managed by the Romanian Digitalisation Authority and is an official website of the Romanian Government
Public Institutions
Need assistance?
EU Institutions
Info
Your Europe
PNRR
PNRR. Finanțat de Uniunea Europeană
UrmătoareaGenerațieUE
© 2024 roepas.ro