The Central Unit or Territorial Branch of Land Improvement coordinates the procedural activity regarding the issuance of approvals in compliance with the legal provisions in force.
*Entitled persons
Regulated professions
Required documents
Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
-
The request of the beneficiary or the owner, as applicable, specifically mentioning the area, the investment to be made, signature*
Descarcă
Copy of the identity document*
Descarcă
Notarial power of attorney/delegation/general assembly decision of the associations, the sole associate’s decision/representative of the associative form, in copy, copy of the ID card of the authorized person, natural person or passport for the authorized person with domicile abroad*
Descarcă
In case of representation Following the notification of the issuance of the permit, the original documents will be presented when picking it up from the office*
Copy of the ownership deed or another valid land possession document, concluded with a notarial authentication*
Descarcă
Examples: The ownership title, sale-purchase contract, donation contract or concession, lease, rental, superficiary contract will be presented*
Copy of the urban planning certificate (valid), accompanied by the zoning plan and the site plan*
Descarcă
Proof of payment*
Descarcă
Payment can be made through the following methods: - cash at the central unit - bank transfer at the bank unit - treasury ANIF ACCOUNT: FTIF Dolj RO22TREZ291501701X017185*
Land registry excerpt*
Descarcă
The land registry excerpt for information accompanied by the excerpt from the cadastral plan, issued by the office of cadastre and real estate publicity no more than 30 days prior to the date of submitting the documentation (except in the case where the issuance of the construction permit is requested for the implementation and rehabilitation of improvement infrastructure in accordance with the provisions of art. 33, para. (2), letter a) of Law 138/2004 with subsequent amendments and additions).*
Copies of payment documents*
Descarcă
The technical project must be approved by the Technical-Economic Council of ANIF if the beneficiary's construction is located on Land Improvement works*
Descarcă
*
Registration certificate*
Descarcă
Certificate of registration from the trade registry or the document based on which it carries out its activity, in copy*
Descarcă
The owner's consent for the permanent or temporary removal of the land from the agricultural circuit or the administrator’s consent for the permanent or temporary removal of the land from the agricultural circuit*
Descarcă
The first agreement will be sent as a copy, in case the land is owned by another person than the owner. The second agreement will be sent as a copy, in case the land belongs to the public/private domain of the state, and also, following the notification for the issuance of the permit, the original document will be presented when collecting it from the office.*
Fees
Title
Payment method
Value
Currency
Taxă fixă
OP
337.12
Deadlines
Resolution time:
5
Calendar days
Case filling duration:
15
Calendar days
Notification deadline:
4
Calendar days
Legislation
- Law number
83
dated year
2018
ORDER no. 83 of February 23, 2018 for the approval of the Procedure regarding the permanent or temporary removal from the agricultural circuit of lands located outside the built-up area of localities, as well as for the approval of the Procedure regarding the refund of the fee paid to the Land Improvement Fund.*
- Law number
83
dated year
2010
Emergency Ordinance no.83 of 2010 regarding the exemption from payment of the fees provided in art.42 para (3), letter h of the Land Improvement Law no.138 of 2004, for the removal of land necessary for the achievement of certain objectives of national, county, and local interest from the agricultural circuit*
Appeal routes
National legislation does not contain special provisions; in the case of a dispute, the common law provisions apply.
Additional information
More info:
Links
None
Assistance and problem-solving services
None
Last updated:
27 July 2022
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Institution responsible with document:
Publicat de către:
A paragraph is a self-contained unit of a discourse in writing dealing with
a particular point or idea. Paragraphs are usually an expected part of
formal writing, used to organize longer prose.
Anif Territorial Branch of Land Improvements Dolj*
*Content marked with an asterisk (*) has been automatically translated and may not fully reflect the original meaning. For objective interpretation, please consult the Romanian version.
Str. Mihai Eminescu nr.16, Cod poștal 207550
Telefon:
0251 429927
Fax:
0251 429184
Email:
dolj@anif.ro
Table of contents
Competent entities
Biroul Operational
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve