Useful information for connection to the electricity distribution network (steps to follow):
-submitting the connection application and the necessary documents (application for issuing the Technical Connection Notice-ATR, site approval application, documentation depending on the category of the construction or installation)
-establishing the solution for connecting to the network
-issuing the ATR - valid for 12 months from the date of issuance
-requesting the connection contract and choosing the operator who will design/execute the electrical installation
-design and execution of the connection works. The start of execution works is done only after:
a) the connection fee is paid,
b) the construction permit for the objective is presented,
c) the construction permit for the connection works is obtained,
d) the superficies/use/servitude contract is concluded as applicable
-commissioning
-submitting the usage installation file
-issuing the connection certificate
-final energizing and connection
*Denumire
Descriere
Obligatoriu
Semnătură digitală
Tip document
Descarcă
Title
Payment method
Value
Currency
In the event of a dispute between the beneficiary and the competent authority, the provisions of common law are applicable.
*Competent entities
Share your opinion
Provide your opinion about the content of this page. You can leave acomment about what we can improve. You will not receive a response toyour comment. Use the contact form to clarify any questions regardingthe information and services available on this portal.
Did you find what you were looking for?
Help us improve